Report for February 2017
- Report Date
- February 2017
Overview
Achievements in Last Period
- design and technical meetings - achieved
- T&C's - achieved
- no amber or red risks
Next Steps
- updated plan with confirmed booking for ITI and Apps
- confirm budget extra spend for Atlantis and Apps
- documents for project board on 11/4 - scope restated, road map, world UX map
- draft design document
- order kit
Status Green
Future Milestones
31-Mar-2017 | New System Design Complete |
05-May-2017 | Build Complete |
07-Jun-2017 | Pilot Live |
07-Jun-2017 | Start Pilot Service |
28-Jul-2017 | Security Acceptance Sign-off |
31-Aug-2017 | Service Live |
31-Aug-2017 | Deployment of Apps to User Devices - New Service Live |
26-Oct-2017 | Deployment Sign-off of New Service |
26-Oct-2017 | Deployment Sign-off of New Service |
31-Oct-2017 | Sign-off Service Deployment |
10-Nov-2017 | Closure of Project |
- Approved budget
- 140.0 days
- Activity this month
- 2.0 days
- Activity this year
- 69.5 days
- Activity to date
- 69.5 days
- Estimate to complete current year
- 70.0 days
- Estimate to complete future years
- 0.0 days