Report for February 2018

Report Date
February 2018

Summary

The build of the VSAN solution to replace the Atlantis is now complete.

The project plan has been updated and the scheduled dates for completion of build, testing and delivery of the new service, agreed as realistic and attainable by the project team. The project manager has sent an update to the project board early January, to include the new payment schedule and UAT dates.

Good progress in that two long standing technical showstoppers have been fixed.

However, the combination of strikes, change freeze and the weather has meant the cancellation or key meetings and activities, which now have to be rescheduled and resourced. Outcome is not known so we hope to reduce delay but project Amber until new dates are set.

 

Achievements in Last Period

  • netscaler red issue fixed
  • html5 red issue fixed
  • confirm project plan - achieved

Issues and Risks

  • Issue : We need NHS agreement on whitelisting our ports
  • Issue : work planned for 6th March and UAT Workshop need to be rescheduled to new dates  

Next Steps

  • complete Build 16th March
  • UAT workshop 2nd March
  • project board meeting 15th March
  • communication plan draft
  • UAT planning and user engagement

 

Future Milestones

 

29-Mar-2018 Solution Build Complete (payment 3/5)
10-May-2018 GDPR Sign-off
10-May-2018 EQIA Sign-Off
10-May-2018 Security Sign-off
11-May-2018 UAT and Technical Testing Sign-off
18-May-2018 Start Pilot Service
28-Jun-2018 Deployment of Apps to User Devices -Full Service Live (payment 4/5)
23-Jul-2018 Closure of Project (payment 5/5)
02-Aug-2018 Sign-off Full Service Deployment

 

Project Status AMBER as the Remedial work planned for 6th March has been moved to end of March due to Change Freeze through March. We hope the impact to key milestones will be minimal as UAT is not delayed by too much.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue : the combination of strikes, change freeze and the weather has meant the cancellation or key meetings and activities, which now have to be rescheduled and resourced. Outcome is not known so we hope to reduce delay but project Amber until new dates are set.
Change Status
Activity
Approved budget
116.0 days
Activity this month
0.0 days
Activity this year
58.0 days
Activity to date
58.0 days
Estimate to complete current year
70.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance