Report for November 2018

Report Date
November 2018

Summary

Limited progress made during November due to unavailability of the project manager and limited updates on the outstanding queries:-

  • Technical testing scheduled to commence in Feb 2019 once brocade network project has handed over to service (expected end of Jan 2019) - exact date still to be confirmed by CISX05 Brocade project.
  • No updates on progress of UAT activities from the CSE and CMVM areas
  • USD Helpline team have confirmed that January is not a suitable option for training - awaiting feedback on what date/times would be suitable from February onwards.

Project will only go back to overall RAG status of green once...

  • Brocade dates have been confirmed
  • On-site training dates have been scheduled for all three groups
  • An update and agreed timescales for testing efforts under CSE and CMVM colleges has been established

 

Achievements in Last Period

  • Receipt of graphics and logo files for use on EdWeb site
  • Updated  low-level design (LLD) and technical architecture document (TAD) review in progress by ENT team (95% complete) - expected to complete by end of December

 

Next Steps (December/January)

  • PIA approval ( with service owner and sponsor for final approvals)
  • OLA approval (final draft to be issued for review w/b 03/12)
  • Finalise training dates following confirmation from USD team
  • Support CSE and CMVM colleagues with test preparation and execution activities
  • Issue re-baselined project plan
  • Set date for next project board

 

Future Steps (January+)

  • Approval of communications plan - reminder given at project board in August - to be a specific agenda item for next board meeting.

 

Future Milestones

Stage Milestone Due Date
Integrate Dependency: Brocade 10G Network Ready for Technical Testing       01-Feb-19
Accept Technical Testing Sign-Off 01-Mar-19
Accept UAT Sign-off 29-Mar-19
Deliver Deployment of Apps to User Devices -Full Service Live 29-Mar-19
Deliver Sign-off Full Service Deployment 29-Mar-19
Deliver Service Start 15-Apr-19
Close               Closure of Project 03-May-19

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Project remains as Amber from previous month. Scope will remain amber until commitment from third parties is achieved.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Maurice Franceschi, DTP Programme Manager
Change Commentary
No change to milestone dates from previous month reporting
Activity
Approved budget
122.0 days
Activity this month
2.0 days
Activity this year
25.5 days
Activity to date
147.5 days
Estimate to complete current year
88.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance