Report for November 2019
- Report Date
- November 2019
Summary of Achievements in last period
- Project go live approval delayed
- Progress on actions
- review training videos - reviewed with supplier, further engagement with Digital Skills team in progress
- Access on EUCLID - solution identified and will be implemented week commencing 3rd Nov
- OneDrive visibility- Work around identified and await publishing
- Progress on actions
- Communications Plan updated and with project board for approval
- Complete the update of project plan to reflect new delivery date- Ongoing
- OLA final approval Complete
- CAHSS - await feedback from UAT
- MVM - await sign-off for remaining applications
Note: UAT issues meant the Soft Launch date was not achievable and project will be re-planned once full requirements of training videos have been confirmed
Risks and Issues
No new issues raised
Next Steps (October)
- Project to be re-planned
- Performance/ Load testing to be completed
- 'delta' document outlining the infrastructure testing to be completed with signed off testing
- Communications Plan approval
- Agree go live date
- schedule project board meeting for pre-go live
- Approved budget
- 102.0 days
- Activity this month
- 5.5 days
- Activity this year
- 14.0 days
- Activity to date
- 198.0 days
- Estimate to complete current year
- 94.5 days
- Estimate to complete future years
- 0.0 days