Report for Febuary 2019

Report Date
February 2020

 Summary of Achievements in last period

  • Progress on actions 
    • Technical issue affecting Apps Ed now resolved enabling delivery of Soft Launch
    • Soft launch completed as scheduled - 3rd February 2020
    • MVM students moved from old service
    • Old service decommissioned

 

Risks and Issues

No new issues raised

 

Next Steps (Feb to May)

  • Project activity stand still period to gather and analyse feedback from Soft Launch
  • Schedule communications for go live
  • Schedule Project Board meeting for post-soft launch
  • Schedule closure activities
  • Attain approval for project closure

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
102.0 days
Activity this month
1.0 day
Activity this year
26.0 days
Activity to date
207.5 days
Estimate to complete current year
86.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance