Report for April 2020

Report Date
April 2020

 Summary of Achievements in last period

  • Progress on actions 
    • This project is on temporary hold due to the disruption caused by the Corona Virus.

 

Risks and Issues

Potential disruption from Corona Virus may impact on ability to deliver to the project timeline

Issue

Activities to support home study and home working  has impacted on Desktop Services availability to enable delivery in the planned timeline

 

Next Steps 

  • Draft and schedule communications for go live
  • Re-schedule Project Board meeting for post-soft launch
  • Schedule closure activities
  • Attain approval for project closure

 

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
Reason for Amber status: Impact of Covid-19 risk has caused project to be delayed until the situation is better understood.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
102.0 days
Activity this month
1.5 days
Activity this year
27.0 days
Activity to date
209.5 days
Estimate to complete current year
85.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance