Report for November 2020

Report Date
November 2020

Summary of Achievements in last period 

  • review support with DST, Softcat, Helpdesk - under way

 

Risks and Issues

N/A

 

Next Steps 

  • complete review of support with DST, Softcat, Helpdesk
  • close project

 

Future Milestones

 

Closure                        04-Nov-2020 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
102.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
209.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance