Software Entitlement - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2016 BLUE 0.0 days 0.0 days 0.0
Content
Status
Withdrawn
Current Stage
Initiate
Start Date
Monday, 29 February 2016
Close Date
Friday, 21 April 2017
Project information
Project Code
DTP005
Programme
ITI - Desktop Services (DST)
Session
16/17
15/16
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Programme Priority
8