Supported Desktop for Mac - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2017 BLUE 0.0 days 0.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Friday, 29 April 2016
Close Date
Tuesday, 17 January 2017
Project information
Project Code
DTP007
Programme
ITI - Desktop Services (DST)
Session
16/17
15/16
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Programme Priority
7
Overall Priority
Normal