Report for March 2019
- Report Date
- March 2019
Achievements in Last Period
- SDX - Windows 10 Wipe and Load (Compliance hardware) task sequence tested and signed off by Programme Board
- Communications issued out to migration coordinators SDX - Windows 10 Wipe and Load using USB media now available
- In Place Upgrade - Alpha Release available from 11th March to commence testing by COs expected feedback by 29/03/19 to inform next release
- Training Room Build sign off by LST and Digital Skills and migration dates agreed for AH training rooms EW09 and EW13
- Risk review completed with Project Sponsor and Service Owner
Issues and Risks
Issues :
- Resource for project team remains a key issue
- Support Matrix has been developed along with SDX (with the view that an additional 2 FTE resource would be in place within DST team) this remains an issue for both service and project delivery
- ISFM Departmental managed labs - remaining devices have been escalated with College IT and COs from schools. Those remaining on W7 are documented.
- Operations level agreement not signed off as USD require analyst work completed around resource required within IS Helpline to support proactive monitoring
- Communication regarding programme delayed due to no project resource available - next update expected in April
- Numbers of devices tested using In Place Upgrade - Alpha release only 49 completed - this needs to be increased and have requested support from College IT reps to raise profile and necessity of testing
- Unidesk call raised for Direct Access - possible impact on Web Search and Discovered, some testing required to assess if issue is with 3rd party supplier or Direct Access
Programme risks are available within SharePoint site under Programme Board Documentation
Next Steps
- Department Managed Labs to complete
- On-going communication to Colleges and Professional Services
- In Place Upgrade - next release available and accepted as version to commence migrations
- Windows 10 desktop accepted as a Service
Future Milestones
ISFM Centrally Managed Labs and Teaching Spaces migrated | April 2019 |
Windows 10 Desktop as a Service is accepted | April 2019 |
Migration Process documented and tested | April 2019 |
Closure | May 2019 |
Project Sponsor Commentary
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days