Report for November 2018
- Report Date
- November 2018
Summary
Report from Consultant received as planned. Options and recommendation considered and route to market decided.
Achievements in Last Period
- confirm requirements met with stakeholders - done
- confirm financing of the product - done
- confirm that deployment will be an Apps run project - done
- replies to SQL Server and Windows questions - done
- complete documents for procurement officer (strategy, service risk, etc.) - almost done
Issues and Risks
- none
Next Steps
- review softcat quote with sponsor and service owner
- complete strategic documents and approval from procurement
- reference site visits
- decision to award to SNOW
Future Milestones
31-Jan-2019 | Award to Supplier |
28-Feb-2019 | Contract T&C Agreed |
26-Apr-2019 | Setup and Configuration |
31-May-2019 | Service Ready |
28-Jun-2019 | Closure |
Project Sponsor Commentary / Approval
none
- Approved budget
- 30.0 days
- Activity this month
- 2.0 days
- Activity this year
- 10.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days