Report for April 2019
- Report Date
- April 2019
Summary
Meeting with Sponsor, ITI Director and Service Owner. The outcome of our site visits is that it is recognised that additional 2-3 FTE are required to maintain, support and develop SNOW once purchased.
Maurice and Graham have been asked to lead on providing a business case for additional staff, for the SLT meeting mid-May.
Achievements in Last Period
- decision on award to SNOW - meeting held
Issues and Risks
- none
Next Steps
- prepare business case
Future Milestones
Award to Supplier | 31-May-2019 |
Contract T&C Agreed | 28-Jun-2019 |
Closure | 19-Jul-2019 |
Project Sponsor Commentary / Approval
none
- Approved budget
- 30.0 days
- Activity this month
- 0.0 days
- Activity this year
- 10.0 days
- Activity to date
- 17.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days