Report for May 2019

Report Date
May 2019

Summary

 

Project is to close, without procuring SNOW.

ISG management did not approve funding of additional staff that are needed  to effectively support the new ITAM Service.

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
0.0 days
Activity this year
10.0 days
Activity to date
17.0 days
Estimate to complete current year
13.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Software Assset Management Procurement
Code
DTP016
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Libby McCue
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
10-Jan-2018
Planning Date
30-Apr-2018
Delivery Date
24-May-2019
Close Date
24-May-2019
Overall Priority
Higher
Category
Discretionary