Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2022 BLUE 0.0 days 0.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 7 May 2018
Planning Date
Monday, 11 June 2018
Delivery Date
Tuesday, 16 August 2022
Close Date
Friday, 26 August 2022
Project information
Project Code
DTP017
Programme
ITI - Desktop Services (DST)
Session
22/23
21/22
20/21
19/20
18/19
17/18
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Discretionary
Project Classification
Grow
Project Type
Implementation
Project Size
Medium
Project Complexity
Standard
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
People
Funding Source
ITI Core
Overall Priority
Normal
Student Impact
Project deliverables will be used by students