Report for February 2019
- Report Date
- February 2019
Achievements in Last Period
- Project planning underway
- Project Brief v1.4 created and issued for review - feedback pending from Project co-sponsors
- Meetings held with representatives from CAHSS and CMVM to discuss how we proceed with analysis phase
Risks/Issues
- Risk #1 - DST Resourcing impacting on Delivery Dates
-
Risk #2 - Key resource required across Schools, Colleges and Professional Services
-
Risk #3 - Number of Specialist Device Builds
Next Steps
- Progress planning during March, lining up dates for detailed analysis and subsequent execution phases from information received from colleges
- Engage with contacts from each of the three college areas to progress analysis
- Finalise project brief as v2.0, in time for the next project board
Milestones
- Milestones to be documented once planning stage has concluded
- Note: the delivery and closure dates on the projects website are just placeholders until the planning phase completes
- Approved budget
- 100.0 days
- Activity this month
- 3.0 days
- Activity this year
- 30.5 days
- Activity to date
- 35.5 days
- Estimate to complete current year
- 100.0 days
- Estimate to complete future years
- 100.0 days