Report for May

Report Date
May 2013

Achievements in Last Period

  • The build has been completed and signed off

Issues

  • The timing is User Acceptance Testing has been re-scheduled to avoid exam boards

Next Steps

  • Handover to ECA for User Acceptance Testing
  • Sign Off User Acceptance Testing
  • Deploy to Live in early July

Milestones

 

Target dateTitle
25-Sep-2012Resume Project Work
19-Oct-2012Estimates from Dev Team and Dev Tech
05-Apr-2013Business Requirements Sign Off
06-May-2013System Design Sign Off
24-May-2013Peer Test Sign Off
04-Jul-2013User Acceptance Test Sign Off
08-Jul-2013Deploy to Live
15-Jul-2013Deployment Sign Off Review
17-Jul-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
72.0 days
Activity this month
9.5 days
Activity this year
39.3 days
Activity to date
54.5 days
Estimate to complete current year
18.3 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Infrastrucuture
Code
ECA001
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
20-Oct-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Aug-2013