Closure Review

Project Summary:

 

Contributors

 

 

Role

Department

Name

Project Manager (Owner)

 IS Applications

Craig Middlemass

Programme Manager

IS ApplicationMaurice Franceschi

Production Management Coordinator

IS ApplicationsStuart Craig

Business Area Manager  

ECAClaire Davies

Project Sponsor  

ECAJared Taylor
DeveloperIS ApplicationsJohn Allison

 

Project Review

 

Objectives

The objective for this project was to complete a number of enhancements to the exam boards processes.

Deliverables

All of the enhancements were delivered ahead of the exam boards commencing, with agreement of the project team the Deployment Sign Off was extended to cover all of the exam boards, a number of additional enhancements were raised during exam boards which were built, tested and deployed within a few days, these were:

 

* Degree banding calculation for MFA2 students was not correct due to a bug.

* Bad precision in calculating grade breakdown was causing inaccurate degree banding results for students with certain grade combinations.

* Board reports (all colours) were not ordering by surname as expected.

* File character encoding on Euclid XML and CSV downloads was not set to UTF-8. This caused problems where students had unusual characters in their names.

* Programme VTNGTINTAR1F had no progression recommendation rules associated with it, which caused errors when trying to calculate it.

* UGT 5 cohorts similarly had no progression recommendation rules.

* Refreshing the browser immediately after creating or confirming aggregate grades would result in duplicate sets of grades being created, which cause problems further in the exam board process.

Scope

As stated above all of the agreed enhancements were delivered and a number of additional enhancements were implemented during the post implementation support period.

Schedule

The project did run approximately 2 weeks behind schedule following clarifications of requirements, however, the enhancements were still deployed prior to the start of exam boards.

Analysis of Resource Usage:

Staff Usage Estimate: 45 days

Staff Usage Actual: 49 days

Staff Usage Variance: 9%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

The additional days were due to some clarifications on requirements and a number of post implementation enhancements put in place while exam boards were running.

Key Learning Points:

Having an extended support period worked well with this project as exam boards in particular can bring out exceptional cases that cannot always be accounted for in User Acceptance Testing.

The quick turnaround time on post implementation support was appreciated and was only able to be provided by keeping the developer assigned to the project.

Outstanding issues:

None

Project Info

Project
ECA Exam Board Enhancements
Code
ECA006
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
17-Dec-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary