Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for May May 2013 BLUE
Report for April April 2013 BLUE BLUE BLUE BLUE
Report for March March 2013 GREEN GREEN GREEN GREEN
Report for February February 2013 GREEN
Report for January January 2013 GREEN

Project Info

Project
ECA Exam Board Enhancements
Code
ECA006
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
17-Dec-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary