Report for March
- Report Date
- March 2013
Achievements in Last Period
- Build complete and deployed to Test
- Acceptance Testing commenced
Issues
- Slight delay due to clarification in requirement may need to revise go live if any overrun in Acceptance Testing.
Next Steps
- Complete Acceptance Testing
- Deploy to Live
Milestones
14-Jan-2013 | End of Planning - complete |
28-Feb-2013 | Requirements Sign Off - complete |
08-Mar-2013 | Design Review - complete |
25-Mar-2013 | Build Review - complete |
05-Apr-2013 | Acceptance Test Sign Off |
08-Apr-2013 | Go Live |
15-Apr-2013 | Deployment Sign Off |
19-Apr-2013 | Close |
- Approved budget
- 45.0 days
- Activity this month
- 5.6 days
- Activity this year
- 38.6 days
- Activity to date
- 38.6 days
- Estimate to complete current year
- 6.1 days
- Estimate to complete future years
- 0.0 days