Report for April
- Report Date
- April 2013
Achievements in Last Period
- Testing completed and signed off
- Deployment to live complete, including a last minute change to one of the grade calculations
Issues
- Agreement reached to extend project closure until after the exam boards are complete
Next Steps
- Deployment sign off review
- Close the project
Milestones
14-Jan-2013 | End of Planning - Complete |
28-Feb-2013 | Requirements Sign Off - Complete |
08-Mar-2013 | Design Review - Complete |
25-Mar-2013 | Build Review - Complete |
25-Apr-2013 | Acceptance Test Sign Off - Complete |
29-Apr-2013 | Go Live - Complete |
31-May-2013 | Deployment Sign Off |
07-Jun-2013 | Close |
- Approved budget
- 45.0 days
- Activity this month
- 9.5 days
- Activity this year
- 48.5 days
- Activity to date
- 48.5 days
- Estimate to complete current year
- 0.1 days
- Estimate to complete future years
- 0.0 days