Report for May
- Report Date
- May 2013
Achievements in Last Period
- None awaiting end of exam boards to report on usage of the new features
Issues
- Some issues were raised with calculations during the exam boards these were fixed and exam boards are continuing
- Delay to DSOR due to annual leave
Next Steps
- Deployment sign off review
- Close the project
Milestones
Target date | Title |
---|---|
14-Jan-2013 | End of Planning |
28-Feb-2013 | Requirements Sign Off |
08-Mar-2013 | Design Review |
25-Mar-2013 | Build Review |
25-Apr-2013 | Acceptance Test Sign Off |
29-Apr-2013 | Go Live |
31-May-2013 | Deployment Sign Off |
07-Jun-2013 | Close |
- Approved budget
- 45.0 days
- Activity this month
- 0.1 days
- Activity this year
- 48.6 days
- Activity to date
- 48.6 days
- Estimate to complete current year
- 0.1 days
- Estimate to complete future years
- 0.0 days