Report for May

Report Date
May 2013

Achievements in Last Period

  • None awaiting end of exam boards to report on usage of the new features

Issues

  • Some issues were raised with calculations during the exam boards these were fixed and exam boards are continuing
  • Delay to DSOR due to annual leave

Next Steps

  • Deployment sign off review
  • Close the project

Milestones

 

Target dateTitle
14-Jan-2013End of Planning
28-Feb-2013Requirements Sign Off
08-Mar-2013Design Review
25-Mar-2013Build Review
25-Apr-2013Acceptance Test Sign Off
29-Apr-2013Go Live
31-May-2013Deployment Sign Off
07-Jun-2013Close

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
45.0 days
Activity this month
0.1 days
Activity this year
48.6 days
Activity to date
48.6 days
Estimate to complete current year
0.1 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Exam Board Enhancements
Code
ECA006
Programme
Z. ECA Portal and LMS (ECA) (closed 2012/13)
Project Manager
Craig Middlemass
Project Sponsor
Jared Taylor
Current Stage
Close
Status
Closed
Start Date
17-Dec-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary