Organisation

 

Work/Task Breakdown

  • Initial review of the enhancements for clarification on requirements
  • Estimatation of enhancements for priortisation
  • Prioritisation of enhancements including cut off point for enhancement likely to be delivered in the time available
  • Build of the enhancements including peer testing and deployment
  • User Acceptance Testing of the enhancements delivered - ECA Reps
  • Implementation of enhancements into Production
  • Post go live support - 2 week period

 

Resources Skills and Cost

  • Cold Fusion developer with SQL Server experience - estimates to be confirmed 

 

Project Info

Project
ECA Portal Exam Board Enhancements
Code
ECA010
Programme
CAHSS Portfolio Projects
Project Manager
Craig Middlemass
Project Sponsor
Alan Murray
Current Stage
Close
Status
Closed
Start Date
14-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jun-2014