Report for May 2014

Report Date
May 2014

Achievements in Last Period

  • 2 additional post go live fixes identified and implemented
  • Exam boards now complete for 2013/14
  • Extension to project agreed to early June

Issues

  • No outstanding issues

Next Steps

  • Close the project

Milestones

 

Target dateTitle
06-Jun-2014Project Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
2.5 days
Activity this year
41.5 days
Activity to date
41.5 days
Estimate to complete current year
2.6 days
Estimate to complete future years
0.0 days

Project Info

Project
ECA Portal Exam Board Enhancements
Code
ECA010
Programme
CAHSS Portfolio Projects
Project Manager
Craig Middlemass
Project Sponsor
Alan Murray
Current Stage
Close
Status
Closed
Start Date
14-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jun-2014