Report for March

Report Date
March 2018
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT
Code
EDIP0026
Programme
EDINA
Management Office
ISG PMO
Project Manager
Liz Thomas
Project Sponsor
Janet Roberts
Current Stage
Close
Status
Withdrawn
Start Date
18-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal

Documentation