LitLong - Report for May 2019

Report Date
May 2019
Project Status
RAG Status
Overall
AMBER
RAG Commentary
Awaiting information from third-party supplier. They will not be able to look at our request until mid-June, so project is on hold. There is a risk that the work will not be carried out until after July.
Change Status
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Project timescales are in flux due to uncertainty of third-party timescales for requested information. The project cannot proceed without this information.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LitLong
Code
EDIP0195
Programme
EDINA 20/21
Management Office
ISG PMO
Project Manager
Emily Elliott
Project Sponsor
Janet Roberts
Current Stage
Deliver
Status
In Progress
Project Classification
Grow
Start Date
24-May-2019
Planning Date
n/a
Delivery Date
31-Jul-2022
Close Date
31-Jul-2022
Overall Priority
Normal

Documentation