Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2021 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Key to Choice Redevelopment
Code
EDIP0305
Programme
EDINA 20/21
Management Office
ISG PMO
Project Manager
Emily Elliott
Project Sponsor
Janet Roberts
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
07-May-2020
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jan-2021
Overall Priority
Normal

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard