May

Report Date
May 2017

Achievements this period

  • Project planning has started.
  • Patrick completing training prior to development work starting.

Issues

  • None

Next Steps

  • Complete project planning
  • Set milestones
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdWeb - site audit development
Code
EDWEB002
Project Manager
Bruce Darby
Project Sponsor
Stratos Filalithis
Current Stage
Initiate
Status
Not Started
Start Date
01-Jun-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a