August 2020

Report Date
August 2020
August 2020
 
SCF

2 projects have been proposed, one of which was successful.

Spend is fairly low overall and for this year, however this is mostly down to the impact of Covid-19. It is understood that there is a significant pipeline of projects in Estates.

 

Sustainability Innovation Fund

Started working on a business case for Sustainability Innovation Fund, which was well received by the Utilities Working Group. Further work will be carried in Q1 and Q2 on this.

 

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EEC1 Sustainable Campus Fund (SRS)
Code
EEC1
Programme
SRS - Energy Engagement and Communications (EEC)
Project Manager
Chris Litwiniuk
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2021
Category
Discretionary

Documentation

Not available.