Q1 2019-20

Report Date
November 2019

12 projects have been proposed. Overall, 10 have been approved, including one that was awaiting the decision from previous quarters.

Overall value was £135k, savings £21,8k and payback of 6.2 years.

 

We're continuing to see a good level of engagement with the Fund. A SCF spend prioritisation meeting was postponed until Q2.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EEC1 Sustainable Campus Fund (SRS)
Code
EEC1
Programme
SRS - Energy Engagement and Communications (EEC)
Project Manager
Chris Litwiniuk
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2021
Category
Discretionary

Documentation

Not available.