Winter Shutdown 2019 - update

Report Date
February 2020

The Winter Shutdown 2019 was delivered as planned. Awaiting assessment of success.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Energy Communications
Code
EEC6
Programme
SRS - Energy Engagement and Communications (EEC)
Project Manager
Chris Litwiniuk
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
07-Nov-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.