Distributed vSwitches deployment
- Report Date
- June 2016
Distributed vSwitch deployment is underway and nearly complete. We had an early failure with some Windows Server VMs having failed and so we delayed further deployment while we checked the cause. The issue was discovered to be an issue with a patch on some Windows Servers and not related to the VMware vSwitch deployment and the work is underway and nearly complete.
- Approved budget
- 70.0 days
- Activity this month
- 3.0 days
- Activity this year
- 75.0 days
- Activity to date
- 81.5 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days