Scope and resourcing is still ill defined

Report Date
March 2016

Scope and resourcing for this project is still being defined. As a result the status is RED as there are still too many unknowns.

 

A project manager has been requested

Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Authentication : Review and Harmonisation
Code
ENT002
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
15-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2016
Programme Priority
2
Category
Discretionary