Report for July 2016

Report Date
July 2016

Achievements in Last Period

  • Completed communications planning
  • Undertook and reported on O365 testing
  • Decision on implementation of changes [to go ahead]
  • Clarification on wireless changes

Issues and Risks

  • General risk round timings of implementations
  • Questions round wireless changes (now resolved)
  • Testing required for impact on MyEd mail links (ongoing)

Next Steps

  • Implement ADFS changes
  • Deploy changes to wireless service
  • Decision on implementation of changes to MyEd

 

Future Milestones

09-Aug-2016Deployment of changes (if agreed)Deliver
23-Aug-2016Deployment reviewDeliver
09-Sep-2016Project closure approvedClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Authentication : Review and Harmonisation
Code
ENT002
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
15-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2016
Programme Priority
2
Category
Discretionary