Report for July 2016
- Report Date
- July 2016
Achievements in Last Period
- Completed communications planning
- Undertook and reported on O365 testing
- Decision on implementation of changes [to go ahead]
- Clarification on wireless changes
Issues and Risks
- General risk round timings of implementations
- Questions round wireless changes (now resolved)
- Testing required for impact on MyEd mail links (ongoing)
Next Steps
- Implement ADFS changes
- Deploy changes to wireless service
- Decision on implementation of changes to MyEd
Future Milestones
09-Aug-2016 | Deployment of changes (if agreed) | Deliver |
23-Aug-2016 | Deployment review | Deliver |
09-Sep-2016 | Project closure approved | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days