Report for August 2016
- Report Date
- August 2016
Achievements in Last Period
- Implemented ADFS changes
- Deployed changes to wireless service
- Decision made to implement changes to MyEd
- MyEd changes progressed and user tested
- MyEd changes deployed into Live
- Cross-division group set up to review user experience and instruction
Issues and Risks
- Reported problems for some users on wireless service [addressed & resolved]
- MyEd dashboard link update not implemented straight away [now resolved]
- Some users have problem with uun@ed.ac.uk login [now resolved]
Next Steps
- Roll-out solution to last reported issue
- Review and sign-off changes
- Close project
Project status is Amber because of revised milestones for deployment sign-off and closure.
Future Milestones
21-Sep-2016 | Deployment review | Deliver |
30-Sep-2016 | Project closure approved | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days