New load balancers have been installed, tested, accepted and receipted.

Report Date
June 2016

The load balancers have been installed and tested and passed acceptance testing. The goods have been receipted. 

 

Live service migration is out of scope for this project but is scheduled to occur mid-August.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
10.0 days
Activity this year
32.5 days
Activity to date
32.5 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Load Balancer Procurement
Code
ENT004
Programme
ITI - Enterprise Services (ENT)
Project Manager
Graeme Wood
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
11-Jan-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Jul-2016
Programme Priority
4
Category
Compliance

Documentation