Project Status Reports

Title Report Date Time Cost Scope Overall Change
Closure July 2016 BLUE BLUE BLUE BLUE
New load balancers have been installed, tested, accepted and receipted. June 2016 GREEN GREEN GREEN GREEN
Order has been placed. May 2016 GREEN GREEN GREEN GREEN
April 2016 April 2016 GREEN GREEN GREEN GREEN