March 2016

Report Date
March 2016

Nothing to report this month as waiting on feedback from submitted report. Likely to tie in with the planning for projects 2016-17 as I recommended we investigate hypervisor solution and some capital will be necessary. Hopefully discussion on this will take place during this process. However, note this could still be May/June before we have direction.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Anti-Malware Provision Review
Code
ENT005
Programme
ITI - Enterprise Services (ENT)
Project Manager
Garry Scobie
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
04-Nov-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Apr-2016
Programme Priority
5

Documentation