April report

Report Date
April 2017

 

Achievements in Last Period

There has been no activity on this project this month due to other project activity and also another investigation into service resilience architecture that may provide a better solution to the one being developed here.

The issue we now have is that in order to make SRM work we would need to rearchitect our entire cluster to not present the storage at both sites. Since we are likely to be building a metro-stretch cluster for high availability, this calls into question our strategy of using SRM. The project scope is likely therefore to change without a deployment of a live service and will just report on the issue with a recommendation for further work if we want to use SRM.

Issues and Risks

  • Timescales are affected by the above and milestones have been adjusted as a result though the project is still on track to deliver by the end of July.
  • Testing has shown the failover process to be less automated than may be wished and an alternative approach is being looked at.

Next Steps

  • Continue testing the new storage configuration to see if it resolves the problem.
  • Contact Dell to have it confirmed what we have found.
  • Produce an options report for future deployment based on the restrictions we have encountered and if necessary change scope and milestones.

Future Milestones

24-Feb-2017 16-Dec-2016 Test failover of VMs between JCMB and AT. Integrate  No 

 view

01-Mar-2017 20-Jan-2017 Deploy SRM on DEV VMs for Apps services that they prioritise (date will be determined by them) Accept  No 

 view

13-Mar-2017 03-Feb-2017 Deploy SRM on TEST VMs for Apps services that they prioritise (date will be determined by them) Accept  No 

 view

03-Apr-2017 25-Nov-2016 Document process for building SRM resilience on hosted VMs for critical services Deliver  No 

 view

26-May-2017 No date available  Deploy SRM on LIVE VMs for Apps services that they prioritise (date will be determined by them) Deliver  No 

 view

31-Jul-2017 09-Dec-2016 Project closure and lessons learnt Close  No   
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
problems during various stages of the failover/failback/re-protect testing. There are support calls open with VMware and Dell.
Change Status
Activity
Approved budget
50.0 days
Activity this month
0.0 days
Activity this year
41.5 days
Activity to date
41.5 days
Estimate to complete current year
8.5 days
Estimate to complete future years
0.0 days

Project Info

Project
SRM licenses and Storage Hardware Expansion
Code
ENT009
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Graeme Wood
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
09-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jul-2017
Programme Priority
9
Category
Discretionary

Documentation