August report
- Report Date
- August 2017
Achievements in Last Period
- The documentation is in progress.
- Restoring the service from backup has fully tested.
- The LIVE environment continues to be piloted with DevTech and Edina
- VMware are on site to assist with the build of the extended cluster in Appleton Tower
Issues and Risks
- 10GB network infrastructure has not yet fully been delivered by CIS but we have sufficient connectivity to keep the project on track.
- Full service will be rolled into the continuation project for phase 3 expansion at Appleton Tower, since we have run out of resource for this planning year
Next Steps
- Complete documenting the installation
- Act on feedback from the pilot service to frame requirements for Phase 3 project work-package
- CIS to complete 10GB network infrastructure build
Future Milestones
02-Oct-2017 | Phase 3 design and scope sign off |
31-Jul-2018 | Project closure and lessons learnt |
- Approved budget
- 84.0 days
- Activity this month
- 25.0 days
- Activity this year
- 25.0 days
- Activity to date
- 146.5 days
- Estimate to complete current year
- 59.0 days
- Estimate to complete future years
- 0.0 days