August report

Report Date
August 2017

Achievements in Last Period

  • The documentation is in progress.
  • Restoring the service from backup has fully tested.
  • The LIVE environment continues to be piloted with DevTech and Edina
  • VMware are on site to assist with the build of the extended cluster in Appleton Tower

Issues and Risks

  • 10GB network infrastructure has not yet fully been delivered by CIS but we have sufficient connectivity to keep the project on track.
  • Full service will be rolled into the continuation project for phase 3 expansion at Appleton Tower, since we have run out of resource for this planning year

Next Steps

  • Complete documenting the installation
  • Act on feedback from the pilot service to frame requirements for Phase 3 project work-package
  • CIS to complete 10GB network infrastructure build

Future Milestones

02-Oct-2017 Phase 3 design and scope sign off
31-Jul-2018 Project closure and lessons learnt
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
84.0 days
Activity this month
25.0 days
Activity this year
25.0 days
Activity to date
146.5 days
Estimate to complete current year
59.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Private Cloud Provisioning
Code
ENT010
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Graeme Wood
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Mar-2016
Planning Date
07-May-2016
Delivery Date
15-Nov-2019
Close Date
20-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation