Report for October 2017
- Report Date
- October 2017
Achievements in Last Period
- The documentation is in progress.
- Next phase scope is being drafted
Issues and Risks
- 10GB network infrastructure has not yet fully been delivered by CIS but we have sufficient connectivity to keep the project on track.
- Full service will be rolled into the continuation project for phase 3 expansion at Appleton Tower, since we have run out of resource for this planning year
Next Steps
- Complete documenting the installation
- Rollout to full pilot with any schools/divisions who wish to use it
- CIS to complete 10GB network infrastructure build
Future Milestones
02-Oct-2017 | No date available | Phase 3 design and scope sign off | Design |
31-Oct-2017 | No date available | Full pilot | Build |
30-Nov-2017 | 06-Feb-2017 | Install 10GB switch infrastructure | Build |
26-Jan-2018 | 30-Jul-2017 | End user documentation | Integrate |
25-May-2018 | 03-Jul-2017 | Deliver full service | Deliver |
31-Jul-2018 | 31-Jul-2017 | Project closure and lessons learnt | Close |
- Approved budget
- 84.0 days
- Activity this month
- 25.0 days
- Activity this year
- 25.0 days
- Activity to date
- 146.5 days
- Estimate to complete current year
- 59.0 days
- Estimate to complete future years
- 0.0 days