Report for October 2017

Report Date
October 2017

Achievements in Last Period

  • The documentation is in progress.
  • Next phase scope is being drafted

Issues and Risks

  • 10GB network infrastructure has not yet fully been delivered by CIS but we have sufficient connectivity to keep the project on track.
  • Full service will be rolled into the continuation project for phase 3 expansion at Appleton Tower, since we have run out of resource for this planning year

Next Steps

  • Complete documenting the installation
  • Rollout to full pilot with any schools/divisions who wish to use it
  • CIS to complete 10GB network infrastructure build

Future Milestones

02-Oct-2017 No date available  Phase 3 design and scope sign off Design 
31-Oct-2017 No date available Full pilot Build
30-Nov-2017 06-Feb-2017 Install 10GB switch infrastructure Build 
26-Jan-2018 30-Jul-2017 End user documentation Integrate 
25-May-2018 03-Jul-2017 Deliver full service Deliver 
31-Jul-2018 31-Jul-2017 Project closure and lessons learnt Close 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
84.0 days
Activity this month
25.0 days
Activity this year
25.0 days
Activity to date
146.5 days
Estimate to complete current year
59.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Private Cloud Provisioning
Code
ENT010
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Graeme Wood
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Mar-2016
Planning Date
07-May-2016
Delivery Date
15-Nov-2019
Close Date
20-Dec-2019
Overall Priority
Higher
Category
Compliance

Documentation