Report for October 2019
- Report Date
- October 2019
Achievements in Last Period
- End user documentation and service documentation has been reviewed.
Issues and Risks
- A decision needs to be made on how the service will be billed for.
Next Steps
-
Changing service name with a front-ended URL of grace.hopper.cloud.ed.ac.uk - backend server is hard-coded and not trivial to change
- Deliver full service.
Future Milestones
Deliver | Deliver full service | 15 November 2019 |
Close | Project closure and lessons learnt | 30 November 2019 |
- Approved budget
- 85.0 days
- Activity this month
- 2.0 days
- Activity this year
- 63.5 days
- Activity to date
- 180.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days