Report for December 2019

Report Date
December 2019

Achievements in Last Period

  • Full service delivered.
  • Draft closure report prepared.

Issues and Risks

  • None.

Next Steps

  • None

Future Milestones

None

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Project is back off hold and progressing
Activity
Approved budget
85.0 days
Activity this month
2.0 days
Activity this year
63.5 days
Activity to date
180.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Private Cloud Provisioning
Code
ENT010
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Graeme Wood
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Mar-2016
Planning Date
07-May-2016
Delivery Date
15-Nov-2019
Close Date
20-Dec-2019
Overall Priority
Higher
Category
Compliance