Train ITI/ISG staff in the best practise software development process.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2016 BLUE 31.0 days 21.0 days 0.0

Project Info

Project
Local Software Lifecycle (Unix Services Continuous Improvement)
Code
ENT014
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Kenneth MacDonald
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Start Date
16-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Dec-2016
Programme Priority
23
Overall Priority
Normal
Category
Discretionary

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.