This project will deliver updated tools for the Helpline and others to manage and audit account management that is driven from the IDM into Active Directory. It will also fully document the code and provide user documentation for the use of these tools and commit the code supporting this into subversion for ease of maintenance.

The existing tools no longer work properly and the code is poorly documented. This will ensure that the tools remain fit for purpose and can be maintained into the future. This will improve efficiency by providing the Helpline and other computing staff with the management information needed to support accounts in Active Directory without having to escalate calls to 2nd and 3rd line support.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2017 BLUE 35.0 days 23.0 days 0.0

Project Info

Project
AD Platform Driver
Code
ENT017
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Graeme Wood
Project Sponsor
Murray Dippie
Current Stage
Close
Status
Closed
Start Date
13-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
05-Jul-2017
Programme Priority
27
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard