January 2017

Report Date
January 2017

Achievements in Last Period

  • Consultation phase with stakeholders
  • Create WSUS reporting mechanism
  • Documentation

Issues and Risks

  • Time constraints with this project due to involvement with ENT009 - SRM Licenses and Storage Hardware Expansion

Next Steps

  • Complete build and configure Test infrastructure
  • Complete build and configure Live infrastructure
  • Testing phase

Future Milestones

24-Feb-2017

Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
32.0 days
Activity this month
1.0 day
Activity this year
7.0 days
Activity to date
7.0 days
Estimate to complete current year
25.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Windows Management Platform Continuous Improvement (WSUS)
Code
ENT018
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Murray Dippie
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Start Date
23-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Mar-2017
Programme Priority
24
Overall Priority
Normal
Category
Discretionary