Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2017 BLUE 25.5 days 26.3 days 0.0

Project Info

Project
EASE Web Site Refactor
Code
ENT021
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Jon March
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Start Date
16-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Sep-2017
Programme Priority
11
Overall Priority
Higher
Category
Discretionary