Authorisation improvements including AD review and cleanup and access policy to authorisation information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2019 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Authorisation improvements including AD review
Code
ENT042
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Graeme Wood
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
15-Apr-2019
Planning Date
31-Jul-2019
Delivery Date
03-Aug-2020
Close Date
21-Aug-2020
Overall Priority
Highest
Category
Discretionary

Documentation

Not available.

Project journal

No entries found.

Change dashboard

Nothing to report.