Report for November 2021
- Report Date
- November 2021
Achievements in Last Period
-
New draft report representing progress graphically
-
17 servers decommissioned
-
Contacted owners of 2 servers planned for action in November but not yet completed
-
Contacted owners of 6 servers planned for action by end December
-
Contacted owners of 7 servers planned for action in January
Issues/Risks
Next Steps
-
Updated report on progress to project sponsor and stakeholders
-
Update any dates due to responses from server owners.
Milestones
Approach for managing servers remaining on 2012 after October 2023 approved | 04-Jul-2022 |
Server inventory and comms plan updated for input to annual planning - 2022 | 01-Aug-2022 |
Final upgrades, migrations or decommissioning delivered | 02-Oct-2023 |
Out of support servers management plan delivered | 02-Oct-2023 |
Close | 23-Oct-2023 |
- Approved budget
- 358.0 days
- Activity this month
- 3.0 days
- Activity this year
- 9.0 days
- Activity to date
- 83.0 days
- Estimate to complete current year
- 30.0 days
- Estimate to complete future years
- 248.0 days