Remaining Staffmail users will  be migrated to Office365 under COM055- Staffmail Migration in time for the start of the 2020/20121 academic session.

 

This project will  then decommission Staffmail.  It will also  simplify the mail routing infrastructure and remove and retire legacy information in the mail relays, fully implement DMARC, and deliver an IMAP service for system accounts such as "postmaster".

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2021 BLUE 227.0 days 175.0 days 0.0

Project Info

Project
System Emails & Staffmail Decommissioning
Code
ENT208
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
14-Jan-2020
Planning Date
07-Feb-2020
Delivery Date
31-Aug-2021
Close Date
26-Aug-2021
Programme Priority
3
Overall Priority
Normal
Category
Compliance