Report for July 2021
- Report Date
- July 2021
Achievements in Last Period
- Mail service owner approved switch-off of staffmail servers
- Staffmail servers switched off
- Agreement that some scope will be moved into follow-on project
Issues/Risks
Next Steps
-
Plan which tasks will move into scope of follow-on project
-
Close
Milestones
Milestone | Date |
Retiral of staffmail service complete | 31-Aug-2021 |
Close | 30-Sep-2021 |
- Approved budget
- 227.0 days
- Activity this month
- 1.0 day
- Activity this year
- 89.0 days
- Activity to date
- 172.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 30.0 days